25% of the members. That letter opens the subject.
The order of work
Read this the way you would a society meeting.
This page is the path from the first letter to the new keys. Start at the top. Stop when you recognise your own society. Each step has two lines: what people hear in the hall, and what the file actually contains.
ऊपर से नीचे पढ़ें। पहले सदस्यों का पत्र, फिर सभा, फिर नाप, फिर बिल्डर की तुलना, फिर समझौता, फिर निर्माण। जहाँ आपकी सोसायटी है, वहीं रुकें।
Members ask. The meeting agrees. The plot is measured before any builder is treated as chosen.
02Write the dealArea, money, dates and penalties go into one agreement. Then the plans say who gets which flat.
03Watch the buildingPeople leave the old building only after permission. The office watches quality, quantity and time until the keys.
01 · Before a builder is chosen
The society decides in the open. Then the papers are measured.
51% in the general body. Then the papers are measured.
-
1
At least one in four members asks, in writing
In the meetingA quarter of the flats sign a letter saying the society should take up redevelopment. Corridor talk is not this letter.
In the fileThis is the requisition under Section 79(A). Without it, there is no society process to stand on.
-
2
Just over half the members agree, in the general body
In the meetingThe hall agrees to proceed. People should hear what their own road and plot can support before a builder’s number becomes the only number in the room.
In the fileConsent of at least 51%. Major decisions stay in the general body. The Mumbai rules that set how much can be built are DCPR 2034, including what the road width allows.
-
3
The society appoints its own consultant
In the meetingThat person works for the members. The builder’s team works for the builder. Both can be in the room. They are not the same seat.
In the fileThe consultant is the PMC: feasibility, tender, comparison, the development agreement, and later the watch on site. Mr. Kalpesh Bhatt attends the general body.
Still in 01 · The measurement
Five papers. The smallest size is the one to trust.
The same flat is often written as five different sizes: what you measure, the property-tax bill, the valuer, the old agreement, and the old building plan. This office takes the smallest of those five as the area already used. That stops the society promising extra carpet the papers cannot support. After that, the width of the road decides how much new building the rules allow.
-
4
Put the plot papers on the table first
In the meetingPlot area, the property card, whether conveyance is done, the old occupation-certificate plan, and a check that the physical boundary matches the city survey plan.
In the fileFeasibility starts here. Higher FSI is a result of the road and the relevant DCPR 2034 policy. It is not a mood in the meeting.
What happens after the sizes agree
-
5
Every builder answers the same questions
Society details, plot details, and the terms go on one form. The tender can be public or private. Either way, it is written, so answers can sit side by side.
Still in 01 · Choosing
One chart. Four ways to read every offer.
A visit and a brochure are not a selection. The general body should see the same rows for every builder.
1. The offer itself
Extra area, the corpus fund, rent for the period you are out, and the other money terms. Same rows for every bidder.
In the file this is the commercial offer.
2. Can they carry a job this size
Money strength, and what the real-estate regulator’s record shows.
In the file this is financial and RERA due diligence.
3. The conditions, not the first page
What is promised only if something else happens. The quiet lines are where societies get stuck later.
In the file these are the terms and conditions.
4. How they behave
Their other buildings, how they speak to members, and whether the offer matches the market.
In the file: brand and infrastructure, attitude to the project, and a market review.
-
6
The meeting chooses
In the meetingThe chart is in every hand. The vote is in the hall. A builder who has been “talking to us” is still one line on that chart until the body selects them.
In the fileThe order is feasibility, appoint the PMC, tender, comparison and due diligence, then selection. A consultant appointed after the builder is only narrating a decision already taken.
02 · The written deal
If it is not in the agreement, it is a conversation.
-
7
Five things the agreement must be able to answer
In the meetingWhat money or security is kept aside. By which date each stage should finish. How much area and of what kind. What happens if a date slips. What the society must do, and what the builder must do.
In the fileSecurity, timeline, quality and quantity of the offer, penalties, and the duties of both parties. A balanced development agreement means each side can point to a clause, not only to a speech.
-
8
Then the plans: who gets which flat
In the meetingAllotment is written down. If a member wants a larger flat, that extra area is bought and recorded. It is not a favour in the corridor.
In the filePlanning covers allotment, a workable plan, each member’s requirement, and additional area as a documented purchase.
03 · The building
Leave only when the permission says so. Then keep a record.
-
9
Close the pending points, then vacate
In the meetingPeople move out peacefully after the first building permission, and only when the agreement’s conditions for leaving are met. A rumour is not that permission.
In the fileThe first permission is the IOD. Further work needs the commencement certificate and other MCGM approvals. Those are monitored, not assumed.
-
10
While it is being built: quality, quantity, time
In the meetingThe society should hear what was done, not only what was promised. The method used here is a daily update and a note every two weeks.
In the fileConstruction monitoring covers quality, quantity and timeline against the development agreement.
-
11
The keys are a measurement
In the meetingBefore you take the flat, it is measured together. After you take it, there is a period in which defects are still the builder’s to close.
In the fileJoint measurement, repossession, and the defect-liability period. Occupation certificate applied, or received, is a status of its own. It is not the same sentence as “the building looks finished”.
Words you will hear